1. Organizational culture is best explained as organizational
A) Personality
B) Hierarchy
C) Reporting relationships
D) Background
E) Management style
2
A good project management system provides for defining the interface between the project team and the organization in all the following areas except
A) Authority
B) Allocation of resources
C) Development of project team members
D) Integration of the project into the organization
E) All of these are provided
3
Which of the following is an advantage of a functional project management organization?
A) Maximum flexibility in the use of staff
B) Good integration across functional units
C) Shorter project duration
D) Strong motivation of project team members
E) All of these are advantages
4
MegaComputers, Inc. has assigned a project manager for each of the five new-product teams. The managers as well as the project team members work on the projects on a full-time basis. The structure being used is ________ organization.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
5
Elizabeth is considering how to structure a project team that will not directly disrupt ongoing operations. The project needs to be done quickly and a high level of motivation will be needed in order to do that. For this situation, the ______ organization would be the best choice.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
6
A project management system provides a framework for launching and implementing project activities within a ______ organization.
A) Matrix
B) Balanced
C) Weak
D) Sponsor
E) Parent
7
In which of the following is the balance of authority strongly in favor of the functional managers?
A) Weak matrix
B) Balanced matrix
C) Strong matrix
D) Strong
E) Both C and D are correct
8
Matrix management violates the management principle of
A) Span of control
B) Unity of command
C) Parity principle
D) Empowerment
E) All of these management principles
9
The project structure that is ranked as least effective is _______ organization.
A) Functional
B) Balanced matrix
C) Weak matrix
D) Strong matrix
E) Project
10
From the list below, which is not a primary characteristic of organization culture?
A) Control
B) Team emphasis
C) History
D) Conflict tolerance
E) Risk tolerance
11
Who is responsible for determining how tasks will be done in a matrix project management structure?
A) The functional manager
B) The project manager
C) Both are responsible
D) This is no pattern of who takes responsibility
E) None of these are true
12
The Macintosh development team at Apple is a good example of what kind of project structure?
A) Project
B) Balanced Matrix
C) Project Matrix
D) Functional Matrix
E) Functional
13
The Organizational Culture Diagnosis Worksheet classifies cultural characteristics into all of the following except:
A) Physical characteristics
B) Public documents
C) Behavior
D) Folklore
E) Ethics
14
Which of the following is not one of the typical forms of a project management office?
A) Command center
B) Control tower
C) Resource pool
D) Weather station
E) All of these are typical forms of a project management office
15
Which of the following cultural characteristics relates to the degree to which management focuses on outcomes rather than on techniques and processes used to achieve those results?
A) Risk tolerance
B) Reward criteria
C) Conflict tolerance
D) Means versus end orientation
E) Open-systems focus
“CUSTOM PAPER”
- WE OFFER THE BEST CUSTOM PAPER WRITING SERVICES. WE HAVE DONE THIS QUESTION BEFORE, WE CAN ALSO DO IT FOR YOU.
- Assignment status: Already Solved By Our Experts
- (USA, AUS, UK & CA PhD. Writers)
- CLICK HERE TO GET A PROFESSIONAL WRITER TO WORK ON THIS PAPER AND OTHER SIMILAR PAPERS, GET A NON PLAGIARIZED PAPER FROM OUR EXPERTS
QUALITY: 100% ORIGINAL PAPER – NO PLAGIARISM – CUSTOM PAPER
Why Choose Us?
- 100% non-plagiarized Papers
- 24/7 /365 Service Available
- Affordable Prices
- Any Paper, Urgency, and Subject
- Will complete your papers in 6 hours
- On-time Delivery
- Money-back and Privacy guarantees
- Unlimited Amendments upon request
- Satisfaction guarantee

How It Works
- Click on the “Place Your Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
- Fill in your paper’s requirements in the “PAPER DETAILS” section.
- Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
- Click “CREATE ACCOUNT & SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
- From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.
About AcademicWritersBay.com
AcademicWritersBay.com is an easy-to-use and reliable service that is ready to assist you with your papers 24/7/ 365days a year. 99% of our customers are happy with their papers. Our team is efficient and will always tackle your essay needs comprehensively assuring you of excellent results. Feel free to ask them anything concerning your essay demands or Order.
AcademicWritersBay.com is a private company that offers academic support and assistance to students at all levels. Our mission is to provide proficient and high quality academic services to our highly esteemed clients. AcademicWritersBay.com is equipped with competent and proficient writers to tackle all types of your academic needs, and provide you with excellent results. Most of our writers are holders of master’s degrees or PhDs, which is an surety of excellent results to our clients. We provide assistance to students all over the world.
We provide high quality term papers, research papers, essays, proposals, theses and many others. At AcademicWritersBay.com, you can be sure of excellent grades in your assignments and final exams.