Assess if Spokane Electronics correctly interpreted the earned value metrics.

Based on your review and analysis of the “Franklin Electronics” case study (Kerzner, 2017, pp. 545-547) (ATTACHED BELOW), address the following key discussion topic elements:

 

Assess if Spokane Electronics correctly interpreted the earned value metrics. Explain the rational for your conclusion.

What, if any, other EVM metrics would you recommend? Explain the rational for your recommendation.

FRANKLIN ELECTRONICS

 

In October 2013 Franklin Electronics won an 18-month labor-intensive product development contract awarded by Spokane Industries. The award was a cost reimbursable contract with a cost target of $2.66 million and a fixed fee of 6.75 percent of the target. This contract would be Franklin’s first attempt at using formal project management, including a newly developed project management methodology. Franklin had won several previous contracts from Spokane Industries, but they were all fixed-price contracts with no requirement to use formal project management with earned value reporting. The terms and conditions of this contract included the following key points:

 

• Project management (formalized) was to be used.

 

• Earned value cost schedule reporting was a requirement.

 

• The first earned value report was due at the end of the second month’s effort and monthly thereafter.

 

• There would be two technical interchange meetings, one at the end of the sixth month and another at the end of the twelfth month.

 

Earned value reporting was new to Franklin Electronics. In order to respond to the original request for proposal (RFP), a consultant was hired to conduct a four-hour seminar on earned value management. In attendance were the project manager who was assigned to the Spokane RFP and would manage the contract after contract award, the entire cost accounting department, and two line managers. The cost accounting group was not happy about having to learn earned value management techniques, but they reluctantly agreed in order to bid on the Spokane RFP. On previous projects with Spokane Industries, monthly interchange meetings were held. On this contract, it seemed that Spokane Industries believed that fewer interchange meeting would be necessary because the information necessary could just as easily be obtained through the earned value status reports. Spokane appeared to have tremendous faith in the ability of the earned value measurement system to provide meaningful information. In the past, Spokane had never mentioned that it was considering the possible implementation of an earned value measurement system as a requirement on all future contracts. Franklin Electronics won the contact by being the lowest bidder. During the planning phase, a work breakdown structure was developed containing forty-five work packages of which only four work packages would be occurring during the first four months of the project. Franklin Electronics designed a very simple status report for the project. The table below contains the financial data provided to Spokane at the end of the third month.

 

Totals at End of Month 2 Totals at End of Month 3

 

Work Packages PV EV AC CV SV PV EV AC CV SV A 38K 30K 36K 86K 74K 81K B 176 16K 18K 55K 52K 55K ? 26K 24K 27K 72K 68K 73K D 40K 20K 23K 86K 60K 70K

 

Note: BCWS = PV, BCWP = EV, and ACWP = AC.

 

A week after sending the status report to Spokane Industries, Franklin’s project manager was asked to attend an emergency meeting requested by Spokane’s vice president for engineering, who was functioning as the project sponsor. The vice president was threatening to cancel the project because of poor performance. At the meeting, the vice president commented, “Over the past month the cost variance overrun has increased by 78 percent from $14,000 to $25,000, and the schedule variance slippage has increased by 45 percent from $31,000 to $45,000. At these rates, we are easily looking at a 500 percent cost overrun and a schedule slippage of at least one year. We cannot afford to let this project continue at this lackluster performance rate. If we cannot develop a plan to control time and cost any better than we have in the past three months, then I will just cancel the contract now, and we will find another contractor who can perform.”

Order from Academic Writers Bay
Best Custom Essay Writing Services

QUALITY: 100% ORIGINAL PAPER NO PLAGIARISM – CUSTOM PAPER

Why Choose Us?

  • 100% non-plagiarized Papers
  • 24/7 /365 Service Available
  • Affordable Prices
  • Any Paper, Urgency, and Subject
  • Will complete your papers in 6 hours
  • On-time Delivery
  • Money-back and Privacy guarantees
  • Unlimited Amendments upon request
  • Satisfaction guarantee
SATISFACTION

How It Works

  • Click on the “Place Your Order” tab at the top menu or “Order Now” icon at the bottom and a new page will appear with an order form to be filled.
  • Fill in your paper’s requirements in the “PAPER DETAILS” section.
  • Fill in your paper’s academic level, deadline, and the required number of pages from the drop-down menus.
  • Click “CREATE ACCOUNT & SIGN IN” to enter your registration details and get an account with us for record-keeping and then, click on “PROCEED TO CHECKOUT” at the bottom of the page.
  • From there, the payment sections will show, follow the guided payment process and your order will be available for our writing team to work on it.

About AcademicWritersBay.com

AcademicWritersBay.com is an easy-to-use and reliable service that is ready to assist you with your papers 24/7/ 365days a year. 99% of our customers are happy with their papers. Our team is efficient and will always tackle your essay needs comprehensively assuring you of excellent results. Feel free to ask them anything concerning your essay demands or Order.

AcademicWritersBay.com is a private company that offers academic support and assistance to students at all levels. Our mission is to provide proficient and high quality academic services to our highly esteemed clients. AcademicWritersBay.com is equipped with competent and proficient writers to tackle all types of your academic needs, and provide you with excellent results. Most of our writers are holders of master’s degrees or PhDs, which is an surety of excellent results to our clients. We provide assistance to students all over the world.
We provide high quality term papers, research papers, essays, proposals, theses and many others. At AcademicWritersBay.com, you can be sure of excellent grades in your assignments and final exams.

NO PLAGIARISM